Supervisor ARGOTSINGER offered the following Resolution and moved its adoption:

RESOLUTION AUTHORIZING CONTRACT WITH WILLIAM BRADY CONSTRUCTION FOR CLERK OF THE WORKS SERVICES FOR THE FMCC CAMPUS LABS AND CLASSROOMS PHASE 1 PROJECT (2018 CAPITAL PLAN)

WHEREAS, the 2018 Capital Plan identifies a FMCC Campus Labs and Classrooms Phase 1 Project; and

WHEREAS, a bid award has been made for prime contracts construction work on said project; and

WHEREAS, William Brady Construction Consulting Services has submitted a proposal to provide Clerk of the Works Services for the FMCC Campus Labs and Classrooms Phase 1 Project and has been recommended by College officials to complete said work; now, therefore be it

RESOLVED, That the Chairman of the Board be and hereby is authorized to sign a contract with William Brady Construction Consulting Services of Gloversville, NY, for Clerk of the Works Services for the FMCC Student Union Improvement Project, at a cost of $62.00 per hour not to exceed $20,000.00; and, be it further

RESOLVED, That said contract is subject to the approval of the County Attorney; and, be it further

RESOLVED, That said cost be a charge against H.8020.2497-2100.0870 - EXP-FMCC Campus Labs and Classroom Renovations; and, be it further

RESOLVED, That this resolution is contingent upon the passage of a similar resolution by the Montgomery County Legislature; and, be it further

RESOLVED, That certified copies of this Resolution be forwarded to the County Treasurer, Planning Director, FMCC, Montgomery County Legislature, William Brady Construction Consulting Services, Budget Director/County Auditor and Administrative Officer/Clerk of the Board.

Seconded by Supervisor HOWARD and adopted by the following vote:

TOTAL: Ayes: 477 (17) Nays: 0 Abstentions: 25 (1) (Supervisor Young) Absent: 49 (2) (Supervisors Groff and Waldron)