Supervisor ARGOTSINGER offered the following Resolution and moved its adoption:

RESOLUTION AUTHORIZING CONTRACT WITH WILLIAM BRADY CONSTRUCTION FOR CLERK OF THE WORKS SERVICES FOR THE FMCC PE BUILDING BATHROOMS AND LOCKER ROOMS PROJECT (2018 CAPITAL PLAN)

WHEREAS, the 2018 Capital Plan identifies a FMCC PE Building Bathrooms and Locker Rooms Project; and

WHEREAS, a bid award has been made for prime contracts construction work on said project; and

WHEREAS, William Brady Construction Consulting Services has submitted a proposal to provide Clerk of the Works Services for the FMCC PE building Bathrooms and Locker Rooms Project and has been recommended by College officials to complete said work; now, therefore be it

RESOLVED, That the Chairman of the Board be and hereby is authorized to sign a contract with William Brady Construction Consulting Services of Gloversville, NY, for Clerk of the Works Services for the FMCC PE Building Bathrooms and Locker Rooms Project, at a cost of $62.00 per hour not to exceed $20,000.00; and, be it further

RESOLVED, That said contract is subject to the approval of the County Attorney; and, be it further

RESOLVED, That said cost be a charge against H.8020.2497-2100.0885 - EXP-FMCC Campus Bathrooms & Locker Rooms Renovation; and, be it further

RESOLVED, That this resolution is contingent upon the passage of a similar resolution by the Montgomery County Legislature; and, be it further

RESOLVED, That certified copies of this Resolution be forwarded to the County Treasurer, Planning Director, FMCC, Montgomery County Legislature, William Brady Construction Consulting Services, Budget Director/County Auditor and Administrative Officer/Clerk of the Board.

Seconded by Supervisor BLACKMON and adopted by the following vote:

TOTAL: Ayes: 477 (17) Nays: 0 Abstentions: 25 (1) (Supervisor Young) Absent: 49 (2) (Supervisors Groff and Waldron)

Resolutions