Supervisors WALDRON AND ARGOTSINGER offered the following Resolution and moved its adoption:

RESOLUTION AUTHORIZING CHANGE ORDER NO. 1 WITH DAN’S HAULING AND DEMO, INC. FOR THE DEMOLITION PROJECT AT THE TRYON TECHNOLOGY PARK (2017 CAPITAL PLAN)

WHEREAS, the 2017 Capital Plan included the Tryon Technology Park Building Demolition Project; and

WHEREAS, Resolution 557 of 2017 awarded a bid to Dan’s Hauling and Demo, Inc. for said Demolition Project at the Tryon Technology Park; and

WHEREAS, Dan’s Hauling and Demo, Inc, have identified additional asbestos containing materials in Building No. 29 that were not originally identified during the asbestos survey; now, therefore be it

RESOLVED, That the Chairman of the Board be and hereby is authorized to sign Change Order No. 1 to the contract with Dan’s Hauling and Demo, Inc. of Wynantskill, NY for proper removal of asbestos containing materials at the Tryon Technology Park, as part of the Demolition Project as follows:

Original Contract Amount $100,200.00
Change Order No. 1 + 5,520.00
Revised Contract Amount: $105,720.00

and, be it further

RESOLVED, That said contract shall be subject to the approval of the County Attorney; and, be it further

RESOLVED, That said cost be charged to H.8020.6470-2100.0755 – EXP – FC Shovel Ready Land at Tryon Tech Park; and, be it further

RESOLVED, That certified copies of this Resolution be forwarded to the County Treasurer, County Attorney, Planning Director, Dan’s Hauling and Demo, Inc., Budget Director/County Auditor and Administrative Officer/Clerk of the Board.

Seconded by Supervisor WILSON and adopted by the following vote:
TOTAL: Ayes: 20 Nays: 0