Supervisor ARGOTSINGER offered the following Resolution and moved its adoption:

RESOLUTION AUTHORIZING CHANGE ORDER NO. 1 TO THE CONTRACT WITH C.T. MALE ASSOCIATES FOR THE FMCC CAMPUS LABS AND CLASSROOMS PHASE II PROJECT (2019 CAPITAL PLAN)

WHEREAS, the 2019 Capital Plan identifies a FMCC Campus Labs and Classrooms Phase II Project; and

WHEREAS, Resolution 116 of 2019 awarded bids for Prime Contracts for the FMCC Campus Labs and Classrooms Phase II Project, including a Hazmat Monitoring Contract to C.T. Male Associates in the amount of $13,850.00; and

WHEREAS, inasmuch as said Hazmat Monitoring Contract has reached substantial completion, the Planning Director and Fulton-Montgomery Community College officials recommend Change Order No. 1 to release any contract balance; now, therefore be it

RESOLVED, That the Chairman of the Board be, and hereby is, authorized to sign Change Order No. 1 to the contract with C.T. Male Associates of Latham, NY to release any unused balance for said contract as follows:

        Original Contract Amount.       $13,850.00
        Change Order No. 1 (credit).     - 2,093.98
        Revised Contract Amount        $11,756.02

and, be it further

RESOLVED, That any credit shall be to H.8020.2497-2100.0870 – EXP – FMCC Campus Labs and Classrooms Renovations; and, be it further

RESOLVED, That certified copies of this Resolution be forwarded to the County Treasurer, Planning Director, FMCC, Montgomery County Legislature, C.T. Male Associates, Budget Director/County Auditor and Administrative Officer/Clerk of the Board.

Seconded by Supervisor LAURIA and adopted by the following vote: