Supervisors FAGAN AND CALLERY offered the following Resolution and moved its adoption:

RESOLUTION AUTHORIZING CHANGE ORDER NO. 1 WITH BASELINE KING CORPORATION FOR THE AIRPORT RUNWAY AND TAXIWAY LIGHTING AND FENCING CONSTRUCTION PROJECT (2019 CAPITAL PLAN)

WHEREAS, the 2018 Capital Plan identified a Rehabilitation of Runway and Taxiway Lighting and Fencing Project at the Fulton County Airport; and

WHEREAS, Resolution 223 of 2018 authorized a contract with Baseline King Corporation for Rehabilitation of Runway and Taxiway Lighting and Fencing Project in the amount of $719,607.28; and

WHEREAS, the Federal Aviation Administration (FAA) notified Fulton County of additional flight path tree obstructions that require removal as a result of recalculation of the instrumentation systems at the Fulton County Airport, and

WHEREAS, the Planning Director recommends contracting with Baseline King for the removal of said tree obstructions, inasmuch as that contractor is already on site and available to perform the work; now, therefore be it

RESOLVED, That the Chairman of the Board be and hereby is authorized to sign Change Order No. 1 to the contract with Baseline King Corporation for removal of tree obstructions, as part of the Rehabilitation of Runway and Taxiway Lighting and Fencing Project as follows:
 

Original Contract Amount: $ 719,607.28
Change Order No. 1 + 11,200.00
Revised Contract Amount: $730,807.28

and, be it further

RESOLVED, That certified copies of this Resolution be forwarded to the County Treasurer, Planning Director, 195 Factory (FBO), Budget Director/County Auditor and Administrative Officer/Clerk of the Board.


Seconded by Supervisor BREH and adopted by the following vote:
TOTAL:  Ayes: 15      Nays: 0   Absent: 5 (Supervisors Argotsinger, Born, Handy, Howard, Waldron)

 