Resolution No. 320

Supervisor ARGOTSINGER offered the following Resolution and moved its adoption:

RESOLUTION AUTHORIZING COUNTY TREASURER TO CLOSEOUT CERTAIN CAPITAL PROJECTS

WHEREAS, certain projects identified in prior Capital Plans that have been completed and accounts established for said projects are no longer utilized; now, therefore be it

RESOLVED, That the following capital project work has been completed and the Budget Director recommends that said project be closed out and the remaining balance returned to the following accounts:

A-0881 – County Clerk Technology Improvement Reserve:
H.1325.1325-2100.0910 - EXP – Tax Collection Software - 2018 –
(Approx balance: $6,000.00)

A-0909 – Unrestricted Fund Balance: H.8020.6430-2100.0720 - EXP – Tryon Technology Park and Incubator Center
Phase II – 2015 – (Approx balance: $44,208.00)

H.8020.6470-2100.0755 – EXP – FC Shovel Ready Land at Tryon Tech Park – 2015
(Approx balance: $14,788.00)

H.4010.4997-2100.0860 – EXP – Medical Records Server/Software Upgrade – 2017
(Approx balance: $1,439.00)

and, be it further

RESOLVED, That the County Treasurer and the Budget Director/County Auditor do each and every other thing necessary to further the purport of this Resolution; and, be it further

RESOLVED, That certified copies of this Resolution be forwarded to the County Treasurer, County Clerk, Planning Director, Assistant Public Health Director, Budget Director/County Auditor and Administrative Officer/Clerk of the Board.

Seconded by Supervisor HOWARD and adopted by the following vote:

TOTAL: Ayes: 18 Nays: 0 Absent: 2 (Supervisors Callery and Waldron)