Supervisor ARGOTSINGER offered the following Resolution and moved its adoption:

RESOLUTION AUTHORIZING CHANGE ORDERS FOR VARIOUS CONTRACTS WITHIN THE FMCC CAMPUS LABS & CLASSROOMS PHASE II PROJECT 
(2019 CAPITAL PLAN)

WHEREAS, the 2019 Capital Plan identifies a FMCC Campus Labs and Classrooms Phase II Project; and

WHEREAS, Resolution 115 of 2019 awarded bids for Prime Contracts for the FMCC Campus Labs and Classrooms Building Phase II Project; and

WHEREAS, inasmuch as certain contracts have reached substantial completion, the Planning Director and Fulton-Montgomery Community College officials recommend certain Change Orders to release any project Contingency Allowance balances for use on additional projects for the FMCC Campus Labs and Classrooms Building Phase II Projects; now therefore be it

RESOLVED, That the Chairman of the Board be and hereby is authorized to sign the Change Orders for the FMCC Campus Labs & Classrooms Building Phase II Project as follows:

Tri-Valley Plumbing & Heating (Plumbing)
Original Contract Amount:                                                  $111,500.00
Change Order No. 1 (release part Cont. Allowance)         -     2,500.00
Change Order No. 2 (release bal. Cont. Allowance)          -        700.00
Revised Contract Amount                                                  $108,300.00

Tri-Valley Plumbing & Heating (HVAC)
Original Contract Amount:                                                   $116,500.00
Change Order No. 1(Release part Cont. Allowance)         -      2,500.00
Change Order No. 2 (Release bal. Cont. Allowance)         -     2,500.00
Revised Contract Amount                                                     $111,500.00

AOW Associates, Inc.
Original Contract Amount:                                                   $463,900.00
Change Order No. 1 (Fire Alarm Abatement)                     +    5,000.00
Change Order No. 2 (Release bal. Cont. Allowance)         -     8,987.47
Revised Contract Amount                                                   $459,912.53

Fulmont College Association
Original Contract Amount:                                                  $    7,500.00
Change Order No. 1 (Release Contract Balance)             -     1,077.50
Revised Contract Amount                                                  $    6,422.50 

CME Associates
Original Contract Amount:                                                  $    2,300.00
Change Order No. 1 (Release Contract  Balance)             -     1,500.00
Revised Contract Amount                                                  $       800.00

and, be it further

RESOLVED, That any credit shall be to H.8020.2497-2100.0870 – EXP – FMCC Campus Labs and Classrooms Renovations; and, be it further

RESOLVED, That this resolution is contingent upon the passage of a similar resolution by the Montgomery County Legislature; and, be it further

RESOLVED, That certified copies of this Resolution be forwarded to the County Treasuer, Planning Director, FMCC, Montgomery County Legislature, Tri-Valley Plumbing and Heating, AOW Associates, Inc., Fulmont College Association, CME Associates, Budget Director/County Auditor and Administrative Officer/Clerk of the Board.

Seconded by Supervisor CALLERY and adopted by the following vote:
TOTAL:  Ayes: 483 (17) Nays: 0   Abstentions: 25 (1) (Supervisor Young)
Absent: 43 (2) (Supervisors Kinowski and Waldron)
 